Whether Arbitrator can allow damages for delay in completion of project when parties have agreed otherwise in the agreement?
SHUBHAM BUDHIRAJA[1]
A and B enter into a
contract whereby A agreed to complete the project within the timeline, the
parties also agreed on a clause that in case there is any delay in completion
then other party will not be entitled to any damages. A delayed in completing
the project by 3 years. The arbitral tribunal awarded in favor of B including
the claim of damages for delay. The Delhi High Court
confirmed the arbitrator reasoning that the said clause would not be applicable
where the delay is unreasonable and of a long duration. This exclusionary
clause would not preclude the B from raising a claim for compensation. The
‘Business Efficacy Test’ is required to be applied while considering the exclusionary
clause[2].
(I)
It is well settled that the question as to
interpretation of a clause of a contract falls within the jurisdiction of an
arbitral tribunal. The decision of the arbitral tribunal cannot be interfered
with unless the same is found to be patently illegal or in conflict with the
Public Policy of India.
(II)
The contention that the impugned award is
vitiated by patent illegality as it is based on no evidence is also unmerited.
It is necessary to bear in mind that the Indian Evidence Act, 1872 and the
strict rules of evidence are inapplicable to arbitral proceedings. The Arbitral
Tribunal is required to render a decision after evaluating the material placed
before it.
(III)
The Arbitral Tribunal had accepted the CA Certificate.
Although, he was not examined, the concerned officer had produced the said
Certificate and duly affirmed the quantification. The strict rules of evidence
do not apply to arbitral proceedings and there is considerable discretion
available with the Arbitral Tribunal to take a view on the quality and the
sufficiency of evidence.
Greay
ReplyDeleteGreat
ReplyDelete